MENU

Our News

15.10.2025

DESIGN, SUPPLY & INSTALLATION OF NEW CONTAINERIZED 4.16kV SWITCHGEAR

New switchgear system, featuring five advanced cubicles, is designed to deliver a reliable and efficient connection between the existing 5 kV network and the new turbine supply, ensuring robust protection and precise metering functionality.
The complete medium-voltage (MV) switchgear will be installed within a dedicated enclosure and equipped with a 120 VAC UPS system. It will also include 5 kV Cu/XLPE/SWA MV power cable connections integrated with the existing MV switchgear at the OMT powerhouse, Zueitina Oil Terminal — enhancing operational reliability and energy performance across the facility.

30.09.2025

DESIGN, ASSEMBLY & SUPPLY OF DIESEL UNLOADING STATIONS

We are proud to announce the successful completion of engineering, procurement, prefabrication, assembly, and testing of two diesel fuel unloading skids and two flow metering skids for a new power plant project in Libya.
The diesel fuel unloading skids are designed for efficient transfer of diesel fuel from the unloading station to the storage tank.
Each skid consists of the following major components: two stainless-steel centrifugal pumps, complete piping systems, isolation valves, strainers, pressure switches, pressure gauges, and a steel support frame.
The flow metering skids include positive displacement flow meters, load computers, temperature transmitters, air eliminators, automatic valves, grounding units, piping components, and a steel structure, ensuring precise and reliable fuel measurement.
All skids have been coated with C5 corrosion protection system as per ISO 12944, ensuring durability and performance in harsh environmental conditions.
The end user, Zueitina Oil Company, benefits from plug-and-play installation and simplified commissioning, as the skids were completely engineered, assembled, and tested prior to delivery.
This turnkey approach ensures minimal operational losses, reduced maintenance and calibration costs, and long-term stability of all installed components.

21.08.2025

START OF TANK ERECTION ACTIVITIES

After successfully completing the engineering and procurement phases, Bosna-S Team has launched erection works on two 4,500 BBL diesel storage tanks and four 600 BBL daily buffer tanks for our valued client, Zueitina Oil Company.
This project represents another important milestone in supporting Zueitina Oil Company’s operations by enhancing fuel storage capacity and ensuring fully autonomous operation of two Solar SMT60 mobile power units at the Oil Terminal.

24.06.2025

START OF TANK ERECTION ACTIVITIES

Building on the successful completion of the engineering and procurement phases, Bosna-S Team has begun erection works on two 7,500 BBL caustic soda storage tanks for our esteemed client, Sirte Oil Company.
This project marks a significant step toward enhancing storage capacity and ensuring the independent and efficient operation of Sirte Oil Company’s oil and gas facilities.

17.05.2025

COMMISSIONING & START-UP OF OIL REFINERY

Bosna-S Commissioning Team successfully completed the commissioning and start-up of the Marsa El Brega oil refinery for the client, Sirte Oil Company.
The major commissioned systems included the Distributed Control System (DCS), Emergency Shutdown System (ESD), Fire & Gas Detection System (F&G), FM200 fire suppression system, CCTV, HVAC, instrument air, intercom, and telephone systems..
Upon completion of the commissioning phase, the refinery's pipestill distillation unit was successfully started, producing heavy fuel oil (HFO), diesel, and naphtha, with all control loops operating in automatic mode. Entire control system is driven by modern state-of-the-art DCS with additional layers of protection integrated in SIL 3 rated ESD system..
Prior to commissioning, Bosna-S was responsible for the design, procurement, and installation of the complete control system, which comprised 71 control valves, 8 ESD/blowdown valves, over 300 field instruments, HART communicators, and the necessary fire and gas detectors.

12.02.2025

TANK LOWER DECK & OUTER RIM STEEL PLATES

Design, prefabrication and supply of carbon steel tank plates for the Client, Zueitina Oil Co. Project’s aim is to revitalize the existing tank by replacement of tank lower deck and outer rim plates. Bosna-S Oil & Gas to provide full engineering & procurement services.

23.01.2025

SOLAR POWER SUPPLY (ISO 14001)

With a goal to reduce our reliance on diesel, and as to improve our ISO 14001 performance, have installed smart solar hybrid systems for powering our facilities in remote locations in the oil and gas fields of Libya. By using the durable lightweight solar solution, we can reliably power our operations in harsh conditions and reduce logistic complexity of our operations, at the same time creating a friendly working environment.

18.12.2024

STORAGE TANK HANDED OVER TO CLIENT

Our team was able to successfully commission and hand over a storage tank for crude oil (120,000 BBL) under the supervision of the Handover Committee. The tank has been completely overhauled by repairing/patching roof, bottom and shell plates, tank berm, and applying outer foam insulation of tank shell. Prior to commissioning a vacuum and hydrostatic test were performed.

08.10.2024

TANK SHELL STEEL PLATES

Design, prefabrication and supply of carbon steel tank plates for the Client, Waha Oil Co. Project’s aim is to revitalize the existing tank by replacement of tank bottom, annular, shell and roof plates. Bosna-S Oil & Gas to provide full engineering & procurement services.

16.09.2024

TRAINING COURSE ON DCS & ESD SYSTEMS

As certified channel partner of Yokogawa ,have prepared training materials and notes as to familiarize Client’s operators with Centrum VP and ProSafe RS platform. Training covered the following topics: refinery operating philosophy, emergency shutdown function, overrides and resets, operating screens and operation of shutdown console, hardware and software overview, use of safety manager and application builder, use of simulation and test functions, DCS & ESD system maintenance and control logic hand on exercises. The focus of the training for two groups of operators was to equip them with the mentioned skills to secure smooth operation of supplied systems through Project: “Refinery Control & Electrical Systems Upgrade” for our client, Sirte Oil Co.

11.08.2024

CONTROL VALVES

Supply of 116 control valves for the Client, Arabian Gulf Oil Co. Project’s aim is to re-stock the Messla Oil Field Warehouse. Bosna-S Oil & Gas to provide full engineering & procurement services.

01.07.2024

TRAINING COURSE ON SWITCHGEAR & MCC MAINTENANCE

In collaboration with Schneider Electric, training was provided for 10 technicians and conducted at their Belgrade Training Center and production facilities of their licensed partners for SM6, RM6 and Okken Switchgear. The focus of the training was on maintenance and operation of Switchgears and Motor Control Center supplied through Project: “Refinery Control & Electrical Systems Upgrade” for our client, Sirte Oil Co.

26.06.2024

EAST HARBOUR FIRE FIGHTING PROJECT

Implementation of the multidisciplinary EPC contract including an engineering, design, supply and erection of full firefighting system for East Harbour which consists of product, urea and general cargo jetties. Main system deliverables consist of the firewater, jockey and foam pumps, foam/water tower monitors, fire & gas detection system with ups ac/dc supply and LV switchgear and with emergency remote control center (ERCC) integrated with the existing remote monitoring systems.

17.05.2024

SMART SOLAR HYBRID SYSTEM FOR UNDP CO BIH

Signed contract for full EPC Construction of a Smart Solar Hybrid System with a total power of 60 kWp at UNDP Headquarters Building, Sarajevo, Bosnia and Hercegovina. The system allows autonomous electricity supply of the complete building for daily consumption. Panels were mounted on aluminum and hot-dip galvanized support structures at the headquarters roof and upon commissioning connected to the grid through smart hybrid system.

10.04.2024

OPERATOR TERMINALI FEDERACIJE (OTF)

As a member of Consortium have signed a contract for “Reconstruction of Oil Terminal Bihać”, which consists of 9 tanks for oil storage together with complete automated control for rail wagons unloading and tank trucks loading application and fire fighting for the end Client OTF - Operator Terminali Federacije d.o.o. Sarajevo.

18.12.2024

STORAGE TANK HANDED OVER TO CLIENT

Our team was able to successfully commission and hand over a storage tank for crude oil (565,000 BBL) under the supervision of the Handover Committee. The tank has been completely overhauled by replacing the double deck floating roof, tank berm, and repainting the bottom, shell, and roof plates. Prior to commissioning a vacuum and hydrostatic test were performed.

23.01.2024

INSTALLATION, CONSTRUCTION, COMMISSIONING AND START-UP OF TWO (2) SOLAR SMT60 MOBILE POWER UNITS

Awarded a multidisciplinary EPC contract including an engineering, design and supply of diesel unloading and metering skid, two diesel fuel storage tank (4,000 BBL each), diesel fuel treatment and forwarding skids, daily buffer tanks and diesel boosting skid. Two 8-mVA power transformers will connect the complete plant to the terminal grid and two black start diesel generator sets will provide backup power. After the installation is completed, a power plant will be connected to a control system that was designed and supplied with corresponding field instruments. Bosna-S certified engineers will perform pre-commissioning, commissioning, and start-up.

25.03.2024

SOLAR POWER PLANT - VISOKO

Signed contract for full EPC Construction of an SPP with a total power of 357 kWp at Visoko, Bosnia and Hercegovina. The plant consists of n.660 panels mounted on aluminum and hot-dip galvanized support structures at the warehouse roofs. Upon commissioning the plant will be connected to the grid through a 0.4kV connection.

23.01.2024

INSTALLATION, CONSTRUCTION, COMMISSIONING AND START-UP OF TWO (2) SOLAR SMT60 MOBILE POWER UNITS

Awarded a multidisciplinary EPC contract covering the installation of turbines and balance of plant facilities. The scope covers engineering, design and supply of diesel unloading and metering skids, two diesel fuel storage tanks, diesel fuel treatment and forwarding skids, daily buffer tanks and boosting skids; Two 8-mVA power transformers that will connect the complete plant to the terminal grid and two black start diesel generator sets that will provide backup power. The power plant will be controlled by an in-house designed and programmed control system with corresponding field instruments. Bosna-S certified engineers will perform pre-commissioning, commissioning, and start-up.

21.12.2023

DESIGN & ASSEMBLY OF CUSTODY TRANSFER METERING SKIDS

Successful hand-over of eight terminal fuel batch loading metering skids completely engineered, procured, and assembled at our facility consisting of following major components including: Coriolis flow meter with temperature measurement, air elimination and fuel filtering units, set stop valve, overfill and grounding protection unit and all governed by the load computer. Main benefit for the end Client, OTF – Operator Terminali Federacije d.o.o. Sarajevo is easy installation and commissioning due to completely engineered and assembled skid with low billing loss, maintenance, and calibration costs due to long-term stability of Coriolis meters.

20.11.2023

DESIGN & ASSEMBLY OF CUSTODY TRANSFER METERING SKIDS

Successful hand-over of eight terminal fuel batch loading metering skids completely engineered, procured, and assembled at our facility consisting of following major components including: Coriolis flow meter with temperature measurement, air elimination and fuel filtering units, set stop valve, overfill and grounding protection unit and all governed by the load computer. Main benefit for the end Client, OTF – Operator Terminali Federacije d.o.o. Sarajevo is easy installation and commissioning due to completely engineered and assembled skid with low billing loss, maintenance, and calibration costs due to long-term stability of Coriolis meters.

17.10.2023

CONTRACT AWARD

Upon successful bidding process Bosna-S Oil & Gas Co. has been awarded a Project ”Engineering, procurement and construction of new two tanks for caustic soda storage (7500 BBL each)” for the Client, Sirte Oil Co. Project’s aim is to expand storage capacities by complete erection of a two new caustic soda tanks and connect them to existing piping and control system. Bosna-S Oil & Gas to provide full engineering, management, procurement, construction, and start-up activities.

19.09.2023

TANK SHELL STEEL PLATES

Supply and prefabrication of carbon steel tank shell plates for the Client, Zueitina Oil Co. Project’s aim is to revitalize the existing tank by replacement of tank shell plates. Bosna-S Oil & Gas to provide full engineering & procurement activities.

03.04.2023

CONTRACT AWARD

Upon successful bidding process Bosna-S Oil & Gas Co. has been awarded a Project ”Refurbishment of Tank TK-04 at Tobruq Terminal” for the Client, Arabian Gulf Oil Co. Project’s aim is to revitalize the existing tank by complete replacement of a floating double-deck roof and bottom plates together with an annular ring. Bosna-S Oil & Gas to provide full engineering, management, procurement, construction, and start-up activities.

21.02.2023

SOLAR POWER STATION FOR “ASA HOSPITAL SARAJEVO”

The photovoltaic power station will be constructed on the basis of a fixed-price turnkey EPC agreement between ASA Gradnja d.o.o. and Bosna-S d.o.o. Our Re: Sources Department will fulfill the Operation & Maintenance agreement, as to guarantee the plant’s optimal operation and maximum efficiency.

05.12.2022

POWER SUPPLY AND CONTROL OF WATER WELL PUMP

As per awarded Contract our certified engineers have successfully commissioned and put in operation water well pump by installing frequency converter complete with SIEMENS pump controller and connecting it to YOKOGAWA SCADA system and handed over to Vodovod i kanalizacija d.o.o. Podgorica, Montenegro at B6 Pump Station at Zagorič.

04.10.2022

POWER SUPPLY AND CONTROL OF WATER WELL PUMPOWER FARM AT NEVESINJE

Vodovod i kanalizacija d.o.o. Podgorica, Montenegro has awarded an EPC contract for supply, installation and start-up of power supply and control equipment for the water well pump at B6 Pump Station at Zagorič.

23.09.2022

SOLAR POWER FARM AT NEVESINJE

Signed contract for full EPC Construction of a Photovoltaic Solar Farm with a total power of 250 kWp at Nevesinje, Bosnia and Hercegovina. The plant consists of n.550 panels mounted on aluminum and hot-dip galvanized support structures and upon commissioning connected to the grid through a 0.4kV connection.

15.08.2022

4 STORAGE TANKS HANDED OVER TO BPMC

Under supervision of the Hand Over Committee, our Team has successfully commissioned and handed over 4 storage tanks for JET fuel and Diesel. These are the first new storage capacities built in post-revolution Libya. The project is considered as a major milestone in the reconstruction and upgrading of the country’s oil terminals.

06.06.2022

OPERATOR TERMINALI FEDERACIJE (OTF)

As a member of Consortium have signed a contract for “Reconstruction of Oil Terminal at Blažuj”, which consists of 15 tanks for oil storage together with complete automated control and fire fighting for the end Client, OTF - Operator Terminali Federacije d.o.o. Sarajevo.

04.05.2022

MOTT MACDONALD

In cooperation with Mott MacDonald have submitted final Project Dossiers for CONNECTA-ENE-INFR-BIH-PD+TD-02, Preliminary Design and Tender Dossier for the section in BiH on the Interconnection Pipeline BiH-HR (Zagvozd – Posušje – Novi Travnik with a branch to Mostar) to the Client, BH Gas doo.

08.04.2022

YOKOGAWA RESELLER AGREEMENT

During a visit of Yokogawa Representatives to Bosna-S Head Office a reseller agreement for selling and integration of STARDOOM, Fast/Tools & CI Server, Safety & DCS at Oil & Gas, Power and Renewable Power was signed for territory of Bosnia & Hercegovina and Libya.

11.03.2022

LV SWITCHGEAR DELIVERY

Upon successful FAT at Schneider factory premises, LV Switchgear assembly was shipped and handed over to the Client, Sirte Oil Company.

23.02.2022

PROJECT COMPLETION

EPC Project of three jet fuel and one gasoline tanks at Misurata Depot has been completed and prepared for commissioning and final hand-over to the Clinet, Brega Petroleum Marketing Company.

23.01.2022

YOKOGAWA COOPERATION

Held meeting with Yokogawa Representatives as to provide technical support for DCS/ESD/PLC integration and commissioning at CDU4 Basrah project in Iraq in field of electrical and instrumentation works supervised by our certified Functional Safety Engineer (FS Eng – TÜV Rheinland).